A tired North York retail unit converted into a modern client-facing office with custom millwork, new lighting and HVAC distribution, and an accessible entrance — delivered around the tenant's schedule.

ScopeRetail to office conversion
Duration10 weeks
PermitsHandled by YAREX
Found firstA 30 mm dip across the slab
Northside Commercial — a completed commercial renovation in North York, as built
Northside Commercial — as built
What we found

Drop ceilings stained from old roof leaks, fluorescent troffers, a single washroom at the back, and thirty years of layered flooring.

Under the flooring layers, a 30-millimetre dip across the main floor area. Self-levelling underlayment went down in two lifts before partitions were framed.

A North York retail unit before conversion, with drop ceilings stained by old roof leaks, fluorescent troffers and thirty years of layered flooring
30 mm floor dip
The North York unit after conversion to a client-facing office, with custom millwork, new lighting and HVAC distribution and an accessible entrance
Client-facing office
Where the money went
PhaseAmount
Demolition & slab levelling$11,800
Partitions, acoustic insulation & drywall$24,300
Electrical, data & lighting$27,900
HVAC, washroom & accessible entrance$33,600
Millwork, flooring & finishes$38,700
Permits & management$12,300
Fixed estimate total$148,600

How it ran

01

Investigate

Moisture mapping and a selective opening on day one. Cause-of-loss documented before any pricing.

02

Restore

Structure and waterproofing corrected first, dried to a verified reading.

03

Renovate

Then the finish — millwork, stone and flooring, on an assembly that will hold.

The unit was a former retail space in a North York plaza: drop ceilings stained from old roof leaks, fluorescent troffers, a single washroom at the back, and thirty years of layered flooring. The incoming tenant, a professional services firm, needed a client-facing office with meeting rooms, open workstations, and a reception that made a first impression.

The brief carried a hard constraint: the firm was paying rent from day one, so the schedule mattered as much as the finishes.

Work ran on a building permit with the landlord’s base-building approvals. Demolition took the space back to the deck and slab. New steel-stud partitions framed two meeting rooms and a private office, with acoustic insulation and double drywall on the meeting-room walls. Electrical rough-in delivered new circuits and data conduit to every workstation, and lighting switched to linear LED with zone controls. HVAC distribution was reworked with new ductwork and diffusers to serve the partitioned layout. The washroom was rebuilt to accessibility standards, and the entrance received a power door operator. The centrepiece was the carpentry: a site-built white-oak reception desk and a full millwork wall in the main meeting room, fabricated while the trades ran rough-in so finishing started the day drywall was primed.

The challenge was the slab. Demolition revealed the old flooring layers hid a 30-millimetre dip across the main floor area. Self-levelling underlayment went down in two lifts, adding three days — absorbed by resequencing the millwork installation rather than extending the schedule.

The tenant opened on the date written into the contract, in a space that looks nothing like the plaza unit it started as.

More work

Toronto · 2024
Lawrence Park Kitchen & Main Floor

A full main floor renovation featuring a reconfigured kitchen, engineered hardwood, and custom millwork throughout — after two years of concealed leakage from a failed shower pan above was found on day one.

Toronto · 2024
Rosedale Primary Ensuite

A primary ensuite with heated floors, a custom vanity and a curbless walk-in shower, built on a rebuilt subfloor and a properly sloped, fully bonded waterproofing assembly.

Fixed estimate. Permits handled.
Built on evidence.

No surprises. No shortcuts. A written scope, an itemized number that holds, and permits filed before demolition.

24/7 Response(416) 358-2059Fixed estimate